Laredo Set To
Welcome State-Of-The-Art Federal Courthouse
New $33.7 Million Facility Features
Cutting-Edge Technology Inside And Out
By Mark Rea
While many municipalities have fallen in love with the rehabilitation
and renovation of their historical buildings, the Old West
border town of Laredo marries that mindset with its feet planted
squarely in the Age of Technology.
As it peers over the border at Mexico, Laredo has enjoyed
the fruits of expansion over the past decade as the North
American Free Trade Agreement helped swell its population
and city treasury with the almost limitless exchange of goods
with its neighbor.
With the growth has come the pains that any city experiences
in such a boom, including corruption, drug trafficking and
an influx of illegal aliens. As a result, the city is welcoming
a new $33.7 million federal courthouse featuring five cherry-trimmed
courtrooms, five different types of terrazzo flooring and
state-of-the-art technology both inside the structure and
out.
Sherman-based Mitchell Enterprises Inc. is serving as general
contractor for the 120,000 sq. ft. facility, which broke ground
in February 2001 and is scheduled for completion in July.
The new courthouse will help facilitate the overflowing docket
of cases currently moved through the existing courthouse,
sometimes at a snail's pace.
The new courthouse will be the crown jewel of Laredo with
an exterior of Leander white limestone, generous amounts of
curtainwall ringing the rotunda section and a copper roof
covering the dome.
But it is also what makes up the interior of the building
- specifically the steel frame structure - which sets it apart
from nearly every other facility of its kind in the United
States. Contained in the large concrete-filled exterior square
tube columns is a revolutionary new beam-to-column connection
system that makes the facility virtually impervious to such
potential threats as bomb blasts or earthquakes.
After the terrorist attacks on the World Trade Center and
the Pentagon in 2001 and the Murrah Federal Building in Oklahoma
City in 1995, engineers, architects and builders have attempted
to design structures that can better withstand violent forces.
Based upon research it gained from those events, as well
as earthquakes in its home state, Cypress, Calif.-based SidePlate
Systems Inc. developed a proprietary engineering technology
that can be used in all steel frame buildings for enhanced
blast protection and safety.
The General Services Administration, which serves as the
U.S. government's builder and caretaker of federal buildings,
learned in the aftermath of the Oklahoma City bombing that
structural progressive collapse - not bomb blast pressures
and flying debris - was responsible for over 80 percent of
the deaths that occurred in that event.
And while the birth of the patented SidePlate technology
was in the aftermath of a devastating 1994 earthquake in Northridge,
Calif., its unique properties and connection configuration
that can tie girders together across a blast-failed column
provide the right ingredients to prevent progressive collapse
of a structure subjected to terrorist attacks.
Structural engineer and SidePlate Systems president David
Houghton said the Laredo courthouse's steel frame structure
is designed for both progressive collapse mitigation and for
blast-hardened columns.
The steel side plates used in the technology are especially
designed to provide the building structure with structural
continuity, robustness, ductility and torsional strength against
blast pressures by connecting girders on opposite sides of
a violently compromised column.
Design enhancement on the Laredo courthouse project was introduced
by Steve Punch, who served as structural engineer of record
for the project. Punch elected to use SidePlate's hollow column
design option, which allowed the designer to fill columns
after erection with concrete.
According to Houghton, girder-to-girder structural continuity
across a blast-failed column, as well as "hollow column"
construction, are not possible with alternative traditional
connection systems.
Each plate is made of high-grade steel and, according to
published reports, the design of the new courthouse is such
that an airplane could be flown through the building and it
would not collapse.
In addition to the Laredo courthouse, SidePlate Systems said
its proprietary design has been used on many other strategic
buildings and specialty structures across the country, including
the U.S. Army's new Command General and Staff College in Fort
Leavenworth, Kan., the U.S. Navy's Pacific Command Headquarters
in Hawaii and Sea-Tac International Airport's new 265-ft.-tall
Airport Traffic Control tower and Terminal Radar Approach
Control facility in Seattle.
Initial Construction
The project began with removal of several existing foundations
on the site. Corpus Christi-based Large and Sons Foundation
Drilling Inc. drilled more than 160 piers - averaging in diameter
from 24 in. to 30 in. - to a depth of 60 ft.
The courthouse is being constructed in two distinct wings.
The north wing features a basement with a foundation of pier
caps and structural concrete walls while the south wing has
a slab on grade atop piers with columns imbedded as much as
5 ft. deep.
"Once we poured our piers and pier caps, we immediately
started with the structural steel," said Mitchell Enterprises
superintendent Conrad Qualley. Houston-based Postel Industries
Inc. erected the project's structural steel.
"All of those exterior columns for the north wing are
embedded in the basement walls and contain the SidePlate technology,"
Qualley added. "Once the columns were erected through
the second floor, we started pouring basement walls. Then
came the first floor slab on deck and the second slab was
poured. And then came the third."
Each level pour included approximately 18,000 to 20,000 sq.
ft. The 40,000-sq.-ft. monolithic roof deck was also poured
in one day to a thickness of 6.5 in. "We had two pump
trucks pouring from both sides of the building on the roof,"
Qualley said. "We started that pour about 2 a.m. and
didn't finish until 5 the next afternoon."
More than 10,000 cu. yds. of concrete will be used in the
facility, supplied by Laredo-based Ingram Readymix Inc. Ramos
Concrete of Laredo performed slab placement and finishing
while reinforcing steel was placed by Richard's Rebar Placing
Inc. of San Antonio.
Interior Opulence
Visitors entering the courthouse through the rotunda will
be greeted by 20 exposed columns.
Along the curved walls between the columns will be limestone
benches, specially designed to serve as air-conditioning conduits.
Linear diffusers will be installed into each of the seats
to cool the rotunda on hot, summer days.
On the first level will be an architectural terrazzo floor
depicting the Rio Grande as it meanders its way along the
Texas-Mexico border. The terrazzo will wind from the first
floor of the north wing through the rotunda and then out through
the south wing.
Also on first floor are a visitation room for prisoners and
their families, two isolation cells, two additional holding
cells, a processing room, several offices, locker room areas
featuring shower and changing facilities and a state-of-the-art,
built-in vault for storing equipment, valuables and firearms.
On the upper levels are five courtrooms complete with judges'
chambers, offices, jury rooms and anterooms. There is also
a separate room for grand jury deliberations as well as shell
space for a sixth courtroom. Courtroom facilities on the second
and third floors of the south wing feature a pair of holding
cells and one isolation cell. Second- and third-floor courtrooms
in the north wing have two holding cells each. Additional
holding cells are located on first floor in an area designated
for U.S. marshals.
The facility will feature underground parking for just 35
vehicles. Since judges and their highest-ranking staff members
will use the garage, the underground facility will boast some
of the most up-to-date security systems available.
The workforce at the courthouse was about 150 in late March.
But even through the project was about 85 percent complete,
Qualley said it had yet to reach peak production.
"We have a lot of finish work to do," he said.
"We still have carpeting, access flooring, some ceiling
work, some vinyl flooring, all the cell fronts to put in -
I would say we haven't reached the peak of construction yet.
When we do, I would expect that workforce to grow to at least
200. It will be a big push to the end."
|
PROJECT TEAM
|
|
GENERAL CONTRACTOR: |
Mitchell Enterprises Inc.,
Sherman |
|
LOCATION: |
Laredo |
|
OWNER: |
General Services Administration,
Washington, D.C. |
|
CONSTRUCTION MANAGER: |
3D/International Inc.,
Laredo |
|
ARCHITECT/ENGINEER: |
HDR Inc., Dallas |
|
ELECTRICAL: |
ART Electrical Contractors,
Mercedes |
|
MECHANICAL/PLUMBING: |
LDI Metalworks Inc., Fort
Worth |
|
STUCCO: |
Arahead Inc., San Antonio |
|
LIMESTONE: |
S.S. Smith & Sons
Masonry Inc., Corpus Christi |
|
CURTAINWALL: |
WIN-CON Enterprises, New
Braunfels |
|
TERRAZZO: |
National Terrazzo Tile
& Marble Inc., Houston |
|
DRYWALL, CEILINGS: |
Starcraft Interior Contractors
Inc., Houston |
|