New
College Campus Sparking Rebirth In South Laredo
Satterfield & Pontikes In
Charge Of Building Multi-Structure Complex
By Mark Rea
Construction of a second campus for Laredo Community College
is giving the southern part of that Texas border town a chance
at renewed vitality.
Choosing to locate its new $50 million south campus in an
impoverished neighborhood initially raised some local eyebrows.
But since the June 2002 groundbreaking, the burgeoning campus
has sparked a rebirth in the surrounding area.
"This is a significant moment in higher education for
Laredo, Nuevo Laredo and our surrounding communities,"
said Francisco Martinez Jr., dean of Second Campus Planning.
"As the hometown college for this region, we take a great
deal of pride in being able to locate our new campus in the
southern portion of our city."
Chris Hamilton, project manager for Houston-based general
contractor Satterfield & Pontikes Construction Inc., called
it a bold move on the part of the college's board of trustees
"I think part of the intent of bringing this project
to the south side of Laredo was because this part of the city
is economically depressed as compared to the north side,"
Hamilton said. "The college wanted to bring something
to the south side that would help the socio-economics of this
area. So far, it looks like it is having the desired effect."
Even though the project is still several months from completion,
new developments have already started to pop up around the
area.
"There are restaurants here that weren't here before,
a new high school that was recently completed and there are
strip centers and multi-family developments in the planning
stage around the campus area as well," Martinez said.
Dr. Ramon Dovalina, president of Laredo Community College,
said he believes construction of the south campus will not
only rejuvenate the neighborhood, but much of the Lower Rio
Grande Valley area as well.
"For every dollar invested by our taxpayers in LCC,
the Texas Association of Community Colleges estimates that
we will return $3.87 in economic value," Dovalina said.
"If you apply this formula to the $50 million this campus
will invest in the community, our taxpayers can expect a return
of $193 million."
In November 2000, Laredo voters approved the issuance of
$50 million in bonds to finance the land acquisition and construction
of the LCC south campus. The Texas Legislature kicked in an
additional $250,000 grant for the master plan. Construction
costs are expected to be just over $30 million with the remaining
funds earmarked for land acquisition, equipment purchases,
furniture and athletic fields.
The new campus will feature seven separate buildings encompassing
230,000 total sq. ft. Each of the buildings in the 60-acre
complex has been designated by a letter of the alphabet: Building
A - student services and dining facilities; B - library; C
- classrooms and laboratories; D - child development; E -
industrial technology and the campus' central plant; F - criminal
justice and police training; and G - physical education.
Each building boasts its own individual character as well
as function.
"One of the most interesting facets of this project
is that the construction of all the buildings is very different,"
Hamilton said. "For example, four of the buildings are
slab-on-grade, while the police training facility has a basement,
so you have concrete walls and a pan deck there. Building
C is a combination slab-on-grade and structural concrete with
hollow-core planks, and Building A features elevated concrete,
which consists of columns and beams with hollow-core planks.
"Not only that, you have a combination of concrete masonry
unit walls on the industrial technology and physical education
buildings, while the rest have mainly metal studs and drywall.
The variety of the different types of construction here is
really remarkable."
Getting Started
While the project continues on pace for a December completion,
construction nearly was derailed before groundbreaking. After
several old buildings were demolished and removed from the
site, discovery of high-pressure natural gas lines crisscrossing
the site threatened the project.
"One of the most complex parts of the early construction
phase was relocation of those gas lines," Hamilton said.
"There was some question early on whether we could even
get that done because of the various easement issues. But
with a lot of help from the gas companies, we were able to
get those lines moved properly and that problem was alleviated."
The unusual design of some of the buildings has also been
an unusual hurdle for construction crews to clear.
"Building A, for example, has many odd angles,"
Hamilton said. "It makes the steel detailing and fabrication
process laborious to say the least. But the design on this
project was completed in only 10½ months from start
to construction documents. That has created some interesting
challenges."
Construction has closely resembled a design/build project,
although "I didn't really want to say that," Hamilton
said. "We have had a lot of clarifications and minor
modifications on this project.
But that's in no way meant to be critical of the design team
because they only had about half the amount of time to design
it as we have to build it."
Nevertheless, the project has already received an award for
preliminary design excellence from the American Institute
of Architects. The Houston office of international design
giant Gensler & Associates Inc. served as architect of
record for the project while the San Antonio office of PBK
Architects Inc. was the associate architect.
Part of the reason for such compacted design and construction
schedules revolve around the bond package being used to finance
the project. As part of the package, the facility must be
officially open by next March although school officials expect
classes to begin in advance of that date.
Architectural Flair
The main entrance to Building A features a three-story elevator
lobby with a generous amount of glass curtainwall. The 40,000-sq.-ft.
structure features a mixture of standing-seam roofs, metal
wall panels and modified roofs as well as multiple types of
masonry veneers.
It stands between the buildings housing library and classroom
facilities, each of which has its own architectural flair.
"With its multitude of odd angles, Building A is a far
cry from a straight-up, rectangular, big-box-type building,"
Hamilton said. "Building C is similar in that it has
a lot of odd angles, but it is much larger at about 80,000
sq. ft."
The flooring in the two buildings will feature different
patterns of stained concrete. Crews from San Antonio-based
Specialty Concrete will use a combination of processes including
Cemtint, a staining method using penetration of the surface
rather than chemicals. Cemtint is utilized for a more natural
look and smoother texture.
Serving as one of the new campus' focal points will be the
25,000-sq.-ft. library, encased beneath a metal canopy and
expansive amounts of glass curtainwall, installed by Twin
City Glass of Edcouch.
Also on the north side of the complex is an architectural
water feature. Water flows from west to east in a reflecting
pool along Building B and empties into a pond at the bottom
of the glass curtainwall.
A bell tower is also situated between buildings A and B to
provide another distinctive design feature. Charleston, S.C.-based
Van Bergen will cast a specially designed bell for the tower,
which features a combination of jumbo-sized, red brick with
smooth-faced and some split-faced, cream-colored CMUs. Alpha
Masonry of Mission is serving as the masonry contractor for
the entire project.
By mid-April, crews were averaging 5-10 work schedules with
the workforce expected to approach 300 as peak construction
occurs later this summer.
"Our finishing sequence will be buildings E, D, G, F,
C, B and A," Hamilton said. "Building E contains
the central plant, and since our chilled water has to be online
before the finish work can begin, we will complete it first.
Then, we'll progress from the most important to the smaller
buildings and then on to the most complex.
"Since Building A is the most complex of the seven buildings
because of its many angles, it will be completed last."
Seventeen separate parking areas are also part of the project,
and school officials anticipate a student population of about
3,000 when classes begin next year.
| PROJECT TEAM |
|
GENERAL CONTRACTOR: |
Satterfield & Pontikes
Construction Inc., Houston |
|
LOCATION: |
Laredo |
|
OWNER: |
Laredo Community College |
|
PROJECT MANAGER: |
Jacobs Facilities Inc.,
Laredo |
|
ARCHITECT: |
Gensler & Associates
Inc., Houston |
|
ASSOCIATE ARCHITECT: |
PBK Inc., San Antonio |
|
STRUCTURAL ENGINEER: |
Alpha Consulting Engineers
Inc., San Antonio |
|
MEP ENGINEER: |
Day Brown Rice, San Antonio |
|
CIVIL CONSULTANT: |
Mejia Engineering Co.,
Laredo |
|