Arena
Is Latest In Houston's Long History Of Innovative Sports Venues
Downtown Facility Expected To Draw More Than 2 Million Visitors Annually
By Mark Rea
Houston's new downtown arena fits nicely into the city's
long history of innovative, state-of-the-art sports and entertainment
facilities.
Located just a few blocks south of the George R. Brown Convention
Center and Minute Maid Park, the new arena will be a key part
of the continued revitalization of downtown, drawing more
than 2 million patrons to 200-plus events a year.
The new downtown arena, designed by Kansas City, Mo.-based
HOK Sport+Venue+Event and Morris Architects of Houston, will
seat up to 18,500 people for basketball games, and feature
85 luxury suites on two different levels and 2,900 club seats
with access to luxury amenities. The two main seating bowls
are served by two concourses, with the main concourse at street
level. The large, sunken lower bowl contains over 55 percent
of the overall seating, the largest of any major arena, bringing
fans closer to the game and allowing for walk-down seating.
Amenities include a 150-seat restaurant, ledge dining overlooking
the playing court, two club-seat lounges, banquet space and
significantly increased concession and restroom counts in
contrast to Compaq Center. For suite and club-seat ticket
holders, parking is provided in an adjacent 2,500-vehicle
parking garage with a skybridge link to the arena.
The architectural design of the arena presented numerous challenges
for the Houston-based structural engineering design team of
Walter P. Moore & Associates Inc. and associate engineer
Nathelyne A. Kennedy & Associates Inc. One of the most
significant was the large sunken lower bowl, which places
the playing court nearly 32 ft. below street level over four
city blocks.
Excavated from the site were 315,000 cu. yds. of soil, the
largest such excavation ever performed in Houston. A concrete
drilled-pier retention system with 36-in. diameter piers at
44 in. on center and two levels of tiebacks were used to allow
for excavation to the court level. The drilled piers were
incorporated into the completed structure as the foundation
for the exterior columns.
A shotcrete "skin" wall was applied to the piers
and served as the final basement wall.
The depth of the excavation resulted in portions of the playing
court being approximately 16 ft. into the water table.
Ulrich Engineers Inc. of Houston worked with the design team
to develop temporary and permanent systems that allowed 250
gallons of water per minute to be dewatered from the site.
The ice slab for the Houston Aeros hockey team is supported
on a 10-in., two-way structural slab over void forms with
18-in. drilled piers at 28 ft. on center each way.
Vehicle access to the event floor could not be accommodated
on the site, therefore a ramp and tunnel from the adjacent
arena garage provides access by going under Bell Street and
into the arena.
Cast-in-place concrete was used to structure the elevated
floors of the arena. The main and upper concourse levels use
a 25-in. deep pan joist system. Limited floor-to-floor heights
below the suite level necessitated that this level be structured
with 10-in.-thick, two-way flat plates to maximize the plenum
space and ceiling heights in the suites.
The seating bowls consist of conventional precast seating
units with cast-in-place raker beams for the suite seating
and upper bowl, and steel raker beams for the lower bowl.
The lower bowl construction had to be delayed until the completion
of the main roof to maximize the lay-down space for the roof
trusses. Instead of concrete rakers, steel raker beams were
used to allow for faster erection of the lower bowl after
completion of the roof.
The arena has an oblong, shallow-domed main roof that projects
above the concourse roofs. The main structure of the roof
is one of the signature architectural features. Tapered steel-box-trussed
supercolumns rise from the four corners of the arena to support
the main roof trusses that run diagonally from the supercolumns,
crisscrossing to form a prominent "X."
The main trusses, spanning 390 ft., are steel box trusses
made up of W14 chords and diagonals with an overall depth
of 26 ft. at the ends to nearly 36 ft. at midspan. At approximately
the quarter point of each of the main trusses is a secondary
planar truss - also made up of W14s - that spans 153 ft. on
the east-west side and 110 ft. on the north-south side between
truss legs.
The remainder of the roof is infilled with planar WT truss
girders and steel joists. The roof is stabilized by eight
pairs of steel-braced frames along the length of the perimeter
steel ring beam.
In addition to the challenges of solving the complex geometry
of the roof, it also had to be designed to resist 110-mph
hurricane winds. Fort Collins, Colo.-based Cermak Peterka
Peterson Inc. performed extensive wind-tunnel testing to determine
the design wind pressures for the roof.
The results indicated significant downward pressures on the
main roof, which would have not been required by the wind
provisions of the building code. Because of the sensitivity
of long-span roofs to internal pressures, the effects of broken
glass during a hurricane event were also considered.
Suspended from the main roof are two rings of catwalks, a
huge scoreboard and speaker cluster and end-panel scoreboards.
Also hanging from the north and south ends of the main roof
are two 1,500-sq.-ft. mechanical rooms that house the main
air handler units for the arena bow.
The roof structure also supports a distributed rigging grid
designed for up to 120,000 lbs. of rigging load from an end-stage
or center-stage configuration, accommodating the heaviest
of today's concerts.
When the new Toyota Center opens this fall, it will be one
of the city's premier destinations. With complete accommodations
for NHL hockey, the new building will be key element to Houston's
attempt to attract a NHL team.
The arena will also allow Houston to pursue hosting national
and regional events such as the Big XII basketball tournament,
early rounds of the NCAA Tournament and the NBA All-Star game.
Coupled with Minute Maid Park and Reliant Stadium, the new
arena will complete the cycle for Houston with three new sport
facilities.
Dennis M. Wittry, PE, SE, is managing director of Walter
P. Moore & Associates Inc.'s Houston structural engineering
operations.
|