|
Street Savvy
Downtown Houston Streets Receive
Extreme Makeover
By D.Ann Slayton Shiffler
During the past seven years, downtown
Houston streets have been undergoing an infrastructure and
aesthetic facelift that is transforming the look and ambience
of the Bayou City.
Last spring Contractor Technology Ltd.
and Texas Sterling Construction Co., both of Houston, began
ripping out sidewalks, streets and sewer lines, marking the
beginning of the end of the almost $300 million project over
314 city blocks.
The final two contracts, which involve
rebuilding stretches of Travis, Lamar and Smith streets, are
scheduled to be completed by spring. Seven prime contractors
have taken part in the project that has resulted in a grand
transformation of downtown Houston, featuring below-the-surface
infrastructure improvements and street-level enhancements
that include new sidewalks, architectural and artistic elements,
signage, kiosks, lighting, street furniture, signals and bus-stop
shelters.
The Houston Downtown/Midtown Transit
Streets project is funded by the Metropolitan Transit Authority
of Harris County, the city of Houston and the Federal Transit
Authority. The new infrastructure was designed to serve the
city for at least the next 30 years, said John Mickelson Jr.,
senior director of engineering and construction and chief
engineer for Houston's METRO.
"The Transit Street program was the complete rebuilding
of 14 major streets in downtown and midtown," Mickelson
added.
He said that before street construction
could begin, more than 25 mi. of water and sanitary sewer
lines, 2 mi. of storm sewers and 10 mi. of trench and inlet
drains had to be constructed. "Miles of electrical conduit
have also been installed for new traffic signals and improved
street lighting," he added. "And wider sidewalks
with amenities make a more pedestrian-friendly urban environment."
He described the project as "unprecedented."
And Patrick Dewey, project manager for
Contractor Technology Ltd., said: "It's more or less
been a total reconstruction of the streets of downtown Houston.
For this last phase, we've been removing the streets and a
good portion of the sidewalks and then putting in new water
lines and a new 12-in. distribution line that runs the length
of the project. And there's a 4-in. main waterline to install.
We're also putting in a new sanitary sewer, a new storm sewer
and trench drains at each bus stop."
Dewey and his crews are working on the
north and sound ends of Smith Street, completing five blocks
at a time in "rolling block segments."
"The city has us limited to working
on no more than five blocks at a time," he added. "So
with each segment we move forward one block as the back block
is finished." Dewey said his crews are working an average
of 10 to 12 hours a day, six days a week. While an exceptionally
rainy summer and traffic have affected the schedule, he said
there are other factors to work around on a job of such complexity
and magnitude.
He added that for the most part the project is going smoothly
because his crews have been working for seven years and know
what needs to be done and what to anticipate.
An equipment and supply yard at nearby Franklin Street has
made access to equipment convenient. The job has required
a lot of track and backhoes with breakers and hoe rams as
well as dozers and front-end loaders.
While the current job doesn't require
digging to more than 2 to 5 ft. for the drains and water and
sewer pipe, the equipment needed on the job still gets a workout.
"We are working primarily with the
924 John Deeres, the 325 and 350 Caterpillars and the 316
Back Hoe loaders," Dewey said. "For the deeper stuff
we may bring in a big excavator."
The process for each block is roughly
the same. Crews mill off the asphalt and then come in with
breakers to remove the paving. After workers reach the dirt
level, they complete the infrastructure work, replacing the
sewer and water mains as well as the inlets and trench drains.
Once the new infrastructure is in place, the streets are closed
up and 9 in. of flex base and a 9 in. concrete pavement are
put down.
"It's a standard 3,600-psi concrete
using recycled aggregate-basically the same specs that Texas
Department of Transportation uses," Dewey said.
Almost all of the street, curb and sidewalk
paving is done by hand using mixers and form pouring, and
taking the streets to grade level is cumbersome work.
"There are always unknowns when
you pull up old roadways," Dewey said. "Many times
you have to be creative. There are numerous obstacles, and
not everything you find is shown on the plans."
The Texas Sterling crew, which is currently
completing the Travis Street segment, has found a variety
of artifacts under the streets, including old trolley car
tracks and sheet pilings from older building basements.
"We've had to pull out the original
trolley track bed," said Williams Jones, project manager
for Texas Sterling. "We ran into sheet piling from the
original construction of the old Foley's building. We find
a lot of fiber too that is not shown on our plans."
One of the biggest obstacles for both
contractors has been assuring that the buildings and businesses
along the streets can remain operational, with utility service
always up and running.
"Special care needed to be taken
around Foley's," Jones said. "We don't want to hurt
their business. We have made some special concessions and
we will work with them around the holidays. Something like
this could shut a retailer down"
The Travis Street segment is different
than other downtown streets because additional precautions
must be taken near residences such as town homes and lofts.
Storm sewers and sanitary sewer lines
are much deeper, in some areas as much as 23 ft. with pipes
ranging from 22 to 54 in. in circumference. And intersections
in the area are tough because of the fiber utilities.
"There are lots of challenges, but
nothing that can't be worked through," Jones said.
Both project managers say it is satisfying
to see the finished product, "It's much more pedestrian
friendly and interesting for the person walking along the
city streets," Jones said.
The end result lends a unique flavor
to the streetscape. The new street furniture, street lights
and bus shelters coordinate to create a distinctive artistic
look that incorporates modern and historic features.
"Some historical bricks have been
used in the parking lanes, and farther north more artists'
concepts were brought in," Jones added.
|