|
Sea Change for Dallas Skyline
A team headed by Austin Commercial and Beck Architecture has created a new visual entry to downtown Dallas and tony new accommodations for the employees and clients of Hunt Consolidated.
by Bruce Buckley
 |
Before Hunt Consolidated's new $95 million headquarters building
began to take shape, Dallas-area residents knew something
big was heading downtown. In August a parade of 112 trucks
rolled into the area near Woodall Rogers Freeway and Akard
Street to help crews complete a six-hour 1,200-yd. concrete
pour. With no room for staging on the zero-lot line site,
trucks snaked their way through downtown, circling blocks
as they awaited their turn. For general contractor Austin
Commercial, it was just another day in the development of
this monumental new building.
"We've worn out a lot of flags on this job," said Craig Martin,
project manager with Austin Commercial of Dallas.
Hunt has been a downtown fixture for 70 years, but the company
always worked out of multi-tenant buildings. With changing
business needs and expanding security concerns, Hunt decided
to house all of its various entities - including Hunt Oil,
Hunt Realty, Woodbine Development and its private equity group
- exclusively under one roof for the first time in its history.
Just as downtown has always been home to Hunt, the company
hopes its new building will create a welcome mat for the area's
visitors and residents, said John Scovell, president of Woodbine
Development.
"We have the fortune of being located at the gateway to downtown
Dallas," Scovell said. "This building will change that entry."
|
Closing the Sail The centerpiece
of that vision is a 14-story, 400,000-sq.-ft. office tower,
fronted by a dramatic curved-glass curtainwall façade
dubbed "the sail." The building, which was designed
by Beck Architecture of Dallas, appears like a massive clipper
ship at full speed. The façade bows away from the middle
floors of the building with its highest point reaching above
the roof - the equivalent of 17 stories in the air. As the
curvature joins back with the building - at points near the
ground floor and the roof - it intersects a large ellipse
that appears almost like a mast exposed from the upper and
lower portions of the sail.
The back half of the building is clad in warm yellow granite,
which complements the look of neighboring structures.
Ground was broken on the project in October 2005 with occupancy
expected in October of this year.
Design in Real Time The building
makes a bold contemporary statement, although that wasn't
Hunt's original intent. Company chairman and CEO Ray Hunt
envisioned a traditional design, but decided to let four national
architecture firms offer their opinions through a competition,
said Rick Del Monte, managing director and project designer
at Beck Architecture. Del Monte said that Hunt took an intense
interest in the project from the beginning, even meeting with
architects at an intermediate point in the competition to
offer helpful feedback.
"Ray Hunt told us what his favorite buildings were, and
they tended to be the more dramatic modern buildings than
the historical ones," he said.
After Beck's concept was chosen, Hunt continued to work closely
with the firm to fine tune the design.
"Ray has a keen eye," Del Monte said. "He sat
down and we modeled everything in 3-D on the computer. He
sat at our desks in real time as we modified the pieces until
they were at a point where we were all happy."
 |
Atypical Sequencing With plans
in place, work began at the 300-ft. by 200-ft. zero-lot line
office tower site. Crews excavated 40 ft. deep to accommodate
a two-level underground parking area. Workers had to contend
with multiple, unscheduled utilities entering the site and
they had to dig into one of the area's busier thoroughfares
on three occasions for utility tie-ins. Excavations for utilities
on the bottom were hampered by a rock surface, which had to
be jackhammered.
"It was tedious and set us back a while," Martin
said.
The building sits on cast-in-place footings and 120 4-ft.
piers. As the office tower came out of the ground, work began
on the project's other component, a seven-story aboveground
parking garage. Although sequencing would typically call for
the tower to be built before the garage, Martin said it was
necessary to build both simultaneously because of mechanical
tie-ins between the buildings. Beck didn't want anything on
the roof of the office tower to detract from the top spire
of the sail, so it designed the cooling towers on the garage.
As the structures rose, crews would feed utilities between
the two through a connecting bridge.
"It was critical to get the garage structure done even
though it would sit empty for a large portion of the project,"
Martin said.
By having two structures going up simultaneously, Austin Commercial
was able to expedite delay issues. The same framing contractor
was used on both jobs, for example, so when issues with materials
or labor arose on one job, the contractor could borrow from
the other job. The garage topped out in August with the office
tower following in October.
As floors began to stack, work could begin on the complex
curtainwall. The design calls for a unitized system split
into 6-ft. by 15-ft. panels that incorporate curved thermal
insulated glass and granite. Getting the system together required
an international effort. The panels were manufactured in Toronto
with the glass made in China; the granite is Brazilian, but
was crafted in Spain. To save on shipping expenses, the panels
were sent to Dallas in pieces and assembled there.
"It's the most complex piece of curtainwall I've ever
done," Del Monte said. "It curves in one plane of
elevation and the ellipse intersects and runs through it,"
he said. "The ellipse has closely spaced vertical mullions
that run all the way up and down and the [sail] is horizontal
mullions. The intersection of those two systems was an extremely
complex piece of engineering."
With the shell taking shape, other elements of the design
continue to evolve. Ray Hunt and his team have been as focused
on the building's interior as its design. Scovell said Hunt
hopes to create a homey atmosphere for its employees while
putting its best foot forward for its guests and clients.
"Ray has as much interest in what's inside the building,"
Scovell said. "It doesn't matter if it's the bathrooms
or the artwork on the walls. He's shown the same constant
attention to details."
Plans call for the ground floor to feature a mixture of fountains,
pools and a runnel that will appear to flow around the building
on the front and west elevations. The top floor will feature
an employee dining area. Meeting spaces will also be set on
the top floor.
Jeanne Phillips, spokeswoman for Hunt, said the team hopes
to be able to create a welcoming place for employees, a striking
space for clients and a lasting impression for Dallasites.
"We hope people will be able to look back at this building
years from now and say, 'That was a great time for downtown
Dallas - it was a renaissance for the area.'"
| Key Players |
|
Owner:
|
Hunt Cos., Dallas
|
|
Developer/Operator:
|
Woodbine Development Corp., Dallas
|
|
General Contractor:
|
Austin Commercial LP, Dallas
|
|
Building Architect:
|
Beck Architecture, Dallas
|
|
Interior Architect:
|
Gensler, Dallas
|
|
Curtainwall:
|
Trainor Glass Co., Dallas
|
|
Concrete Formwork & Placement:
|
Capform Inc., Carrollton
|
|
Mechanical & Plumbing:
|
Brandt Engineering, Inc., Fort Worth
|
|
Electrical:
|
Humphrey & Associates Inc., Dallas
|
|
Masonry:
|
Dee Brown Inc., Garland
|
|
Steel Fabrication & Erection:
|
Alpha Industries Inc., McKinney
|
|
Fire Protection:
|
Northstar Fire Protection of Texas Inc., Lewisville
|
|
Drywall:
|
Marek Brothers Systems Inc., Coppell
|
|
Elevators & Escalators:
|
KONE Inc., Moline, Ill.
|
|
Painting:
|
Service Excellence Ltd., Dallas
|
|
Metal Panels:
|
NOW Specialties Inc., Carrollton
|
|
Waterproofing:
|
Centennial Moisture Control, Dallas
|
|
Site Utilities:
|
Tri-Dal Utilities, Southlake
|
|