Two
Cool for School
Gilbane Doing Double Duty on Houston-area High School Jobs
By D.Ann Shiffler
For the second time, the Gilbane Co. of Houston is building
two high school complexes for the same district at the same
time.
In 2000, Gilbane constructed two high school campuses simultaneously
for the Houston ISD. In March 2002 it moved its crews west
of town to begin construction of the $52 million Katy High
School No. 5, and then in March 2003 Gilbane began work on
the $58 million Katy High School No. 6.
No. 5 is scheduled to be completed in June, while No. 6 should
be finished in June 2005.
|
Using a modified repeat design, the two Katy schools are
comparable in structural design and layout, although No. 6
includes a ninth-grade addition. Both feature distinctly different
exterior elevations and front-entry facades.
Building both schools at the same time-one a year ahead of
the other-offers many advantages to the contractor and the
subcontractors, said Brent Ivey, project executive for Gilbane.
The majority of the project teams are the same for both schools,
with the exception of plumbing and mechanical contractors.
"The fortunate thing is the perfect lag time," Ivey
added. "The trade contractors who are on both jobs are
able to flow off of one project to the other, and the specialty
subcontractors didn't have to overcome a learning curve when
they moved on to the second project. And for those not familiar
with either project, we literally have a full-size mock-up,
just down the road. We can bring them over to No. 5 and show
them what needs to be done."
The two high schools were not a package job for Gilbane. Each
project is under a separate contract, funded by different
Katy ISD bond packages. As it happened, Gilbane had begun
work on No. 5 before bidding on No. 6. The company was awarded
the contract for No. 6 about a year later.
"When we started No. 5, they hadn't even passed the bond
for No. 6," Ivey said. The upshot was that when the bond
package was passed, plans for the sixth high school could
be expedited because the design was in place and the land
already owned by the district. Ivey said Gilbane "did
have an edge" when the bid was let.
PBK Architects of Houston designed the two schools, which
feature a rotunda entrance with wings and corridors that radiate
outward.
"Programmatically, the two buildings are very similar
and most of the concepts for No. 6 were based on No. 5,"
said Eric Smith, senior project manager for PBK Architects.
"It's a modified repeat with some fairly significant
differences, especially the exterior.
We completely redesigned the front entrance of No. 6. The
idea was that we wanted each school to have its own personality
and look."
The delivery methods for both high schools are different.
With No. 5, a construction-manager-at-risk delivery method
was used, while No. 6 used a competitive-sealed proposal.
"The first school selection allowed us to participate
in the design phase and develop estimates at various phases,"
Ivey said. "No. 6 was more of a hard bid, and we were
successful in that fashion as well."
While the jobs have not been concurrent enough to realize
savings on materials by ordering them all at the same time,
Ivey said Gilbane has realized economies in many other areas.
"There was an advantage to being able to keep our team
together," he said. "It has been a benefit to have
almost the same staff covering both projects," he added.
"This supervision economy is trickling down to the subcontractors
who have superintendents and field personnel who can go from
one job to the other."
While No. 5 is on an approximately 75-acre site, No. 6 is
on a 128-acre site. Each main building includes about 500,000
sq. ft. covering two floors. The buildings features typical
steel construction and masonry cladding on a drilled pier
foundation with grade beams and slab-on-grade. Interior spaces
are separated with either CMU walls or drywall partitions.
Each facility includes a large gymnasium, natatorium and performing
arts auditorium as well as complete athletic facilities including
football, baseball, soccer and other sports.
The main difference between the two buildings is the exterior
facades and the addition of a ninth-grade building for No.
6.
No. 5 was designed for the possibility of a ninth-grade addition.
(Katy ISD's four other high school campuses have ninth-grade
buildings.)
The entry to No. 5 features a tower, while No. 6 has a façade
entry closer to the building.
"The reason for the distinct differences is to give students
a feeling of their school's unique identity," Ivey said.
"These are the second and third schools to feature this
design. Katy's Cinco Ranch High School also has this design."
That design features a main mall and a two-story rotunda with
an impressive 32-segment skylight. Skylights are used throughout
the buildings to bring in natural light.
Smith, PBK's senior project manager, said the goal with the
design of each Katy school is to meet unique educational needs
in the most economically feasible way.
"These schools were tailored to meet the needs of the
students in this district," he added. "Each school
will have specialized programs. The performing arts centers
are quite impressive. They can operate really big theater
programs."
While both buildings will feature the bells and whistles of
a state-of-the-art high school, Smith said that the Katy ISD
is concerned about not winding up with anything too grandiose.
"This is a district that tends to be frugal in its school-building
efforts," he added.
"Several years ago they developed a long-range facility
plan and have stuck with it.
They have a professional demographer who has been very good
at forecasting their needs."
| Katy
High School # 5 - Project Team |
| ARCHITECT:
|
PBK Architects, Houston |
| GENERAL
CONTRACTOR : |
Gilbane Co.,
Houston |
| CONCRETE: |
Keystone Concrete, Houston |
| ELECTRICAL: |
MH Technologies, Houston
|
| DRYWALL: |
Merritt Brothers Drywall,
Houston |
| STEEL: |
Bludau Steel Fabrication,
Halettsville |
| MASONRY:
|
City Masonry, Houston |
| HVAC:
|
Polk Mechanical, Houston |
| PLUMBING:
|
Harcon, Houston |
| Katy
High School # 6 - Project Team |
| ARCHITECT:
|
PBK Architects, Houston |
| GENERAL
CONTRACTOR : |
Gilbane Co.,
Houston |
| CONCRETE: |
Keystone Concrete, Houston |
| ELECTRICAL: |
MH Technologies, Houston
|
| DRYWALL: |
Merritt Brothers Drywall,
Houston |
| STEEL: |
Bludau Steel Fabrication,
Halettsville |
| MASONRY:
|
City Masonry, Houston |
| PLUMBING
and HVAC: |
CFI Corp., Houston |
|