|
Contractors Working 24/7 to Rebuild Houston
Highways
Bonus Incentives Help Speed Construction
Fast-paced schedules mean contractors
must remain ambitious and stay on target in order to receive
bonus incentives and avoid penalties on two major Houston-area
TxDOT projects with combined contracts totaling more than
$1.6 billion.
By Eileen Schwartz
Providing relief to commuters was the top priority when the
Texas Department of Transportation began to plan for the reconstruction
of the section of Houston's IH-610 Loop known as the West
Loop, located in the city's tony Uptown neighborhood. The
reconstruction of the West Loop encompasses nearly a five-mile
stretch, from US 59 (Southwest Freeway) to IH-10 (Katy Freeway),
where it connects with another major project, the Katy Freeway
reconstruction. Together, the two projects will not only relieve
congestion for motorists, they are also generating a mind-boggling
amount work and revenue for Texas highway contractors.
|
The $225 million West Loop reconstruction project, with an
overall completion date of 2007, includes the renovation of
existing roadway, the addition of new entrances and exits
and the creation of so-called hot links, which are designed
to provide exclusive access into and out of the area while
removing traffic from main lanes. Houston-based Williams Brothers
Construction Co. was awarded the project's three prime contracts:
The IH-610/U.S. 59 interchange, which is nearly complete;
IH-610 from U.S. 59 to Post Oak Boulevard, which is scheduled
to be completed late next year; and IH-610 from Post Oak Boulevard
to the IH-10 interchange where the project overlaps with the
$1.4 billion Katy Freeway reconstruction.
The West Loop's new roads, combined with other regional and
local mobility improvements, will provide motorists with more
lanes and more choices, according to Uptown Houston, a local
county-improvement district dedicated to infrastructure improvements
that has partnered with TxDOT on the project. The goal of
the partnership is to make the area one of Houston's most
accessible and convenient locations in the city. "While
plans will ultimately result in a 25 percent increase in lane
miles, the capacity for more automobiles and better movement
will ease congestion at well-known bottlenecks, particularly
the interchanges at the IH-610/U.S. 59 and IH-610/IH-10,"
said Janelle Gbur, director of public information for TxDOT's
Houston District.
The Katy Freeway project, which broke ground in June of last
year and is scheduled for completion in early 2009, is one
of the largest highway construction projects in the state's
history and the first in the nation to convert a portion of
an interstate highway into toll lanes. The job involves the
reconstruction of approximately 23 miles of IH-10 and approximately
two miles of IH-610 including the IH-10/IH-610 interchange.
Of the nine contracts on that project, Williams Brothers was
awarded two, including the IH-610/IH-10 interchange for $263
million, the largest single-project dollar amount ever let
by TxDOT. Of that amount, about $135 million is included in
the West Loop project cost.
To ensure that quality work is completed rapidly, TxDOT has
instituted a financial incentive/disincentive program for
general contractors for each of the three West Loop projects.
Contractors receive a bonus for each day they complete work
on a major milestone ahead of schedule and are penalized a
similar amount for every day a project is behind. "Whenever
a major milestone is completed, an incentive is earned. There
is an equal disincentive if they go beyond the amount of days
allowed for a major milestone. In addition, they will also
be assessed liquidated damages if they go beyond the total
days of the contract," Gbur said. "The high-incentive
contracting rewards the contractors if they meet deadlines
and severely punishes them if they do not," she added.
The incentive program enabled Williams Brothers to work seven
days a week around the clock to complete ramp work on the
IH-610/U.S. 59 interchange in less than 10 months, 67 days
ahead of schedule. "One of the best things TxDOT has
ever done is to provide an incentive bonus, which in turn
provides a cost reimbursement for the increased expense of
24/7 construction required for fast completion," said
Doug Pitcock, president of Williams Brothers.
The company is currently working at a similar pace to complete
the IH-610/IH-10 interchange, which is used by more than 500,000
vehicles per day. The maximum incentive amount for early completion
of the contract is $11.7 million, while disincentives, including
liquidated damages, could cost the company anywhere from $5,000
to $75,000 per day in penalties.
The fast-tracked job, with a contract of $263 million, is
about six months into a 51-month schedule. "If you break
it down, that's about $5 million per month of work to complete
per month," said Clifford Halvorsen, Central Houston
area engineer for TxDOT. "That's a lot of work. On a
typical job, $1 or $2 million a month is a lot of work."
While the size of crews and duration of work necessary to
meet the project's deadline is about three times that of a
typical job, the interchange work is essentially a typical
urban job being done at a rapid pace, Halvorsen said. "Were
not doing anything differently as far as construction than
we've done on other jobs," he added.
Before construction could get underway, utilities running
under IH-610 had to be relocated. The process had to begin
about a year prior to groundbreaking. Since then the same
utilities have been discovered at a different location but
still in conflict with the project and had to be moved again.
"Then you're faced with a situation where, on a normal
job, you have time to relocate." Halvorsen said. "On
a fast-track job the window of opportunity is not there, and
that can be a real set back."
Because of the job's proximity to the popular Galleria area,
TxDOT has agreed to leave as many entrance/exits of the existing
interchange open for as long as possible. "On the West
Loop we've been allowed to shut down more entrance and exit
ramps, and on similar jobs we'd normally shut down half of
the entrance/exits," Halvorsen said. "But because
of the area's significance and commerce, we're not allowed
to do that." He added that there will eventually be short
closures of 20-40 day durations.
|