|
Pedal to the Metal
Construction of Toyota Plant Rides on Fast
Track
By Rob Patterson
From a distance it may look like
a large barn in the middle of a field. But don't look for
longhorns to roll off the line when production starts at Toyota's
new truck manufacturing plant in San Antonio.
Toyota Motor Manufacturing is driving one of the biggest
construction projects currently under way in Texas.
The 2-million-sq.-ft., $800 million truck manufacturing plant
on the southern outskirts of San Antonio aims to roll its
first vehicle off the line in October 2006. Four contractors
in a pair of partnerships are working to meet that goal under
hard-bid contracts. Construction should finish by December.
"The schedule is aggressive," said Paul Street,
project leader for Toyota Motor Manufacturing. "It's
a continuing challenge to bring costs lower and make the schedule
faster."
A joint venture formed by Walbridge Aldinger of Detroit and
Bartlett Cocke General Contractors of San Antonio is constructing
approximately 60 percent of the building. The partnership
laid the foundation and is responsible for the plant's assembly
building; the pressing, welding and plastics shops; and the
plant office.
Graycor Industrial Constructors of Homewood, Ill., and Thos.
S. Byrne of Fort Worth combined forces for the remaining 40
percent of the structure. The team's major sections are the
paint shop and the building's utilities.
Shopping Locally,
Thinking Globally "Toyota's desire is to source
as locally as we can," Street said. "The overall
requirement is automotive experience. The automotive industry
has schedule and cost concerns that other industries don't
quite have. So we put our requirement on automotive experience
and then Toyota experience.
"We bid people that we've used before and understand
the automotive industry. At the same time, it was understood
that it would greatly behoove their presentation and opportunity
if they came and made a joint-venture relationship with local
contractors."
The structure itself is relatively straightforward: structural
steel frame with insulated metal siding on concrete slab topped
with a PVC membrane roof. One unique aspect of the complex
is its single-slope roof with gutter downspout systems and
no roof drains. An equipment gallery on the roof will enclose
all the HVAC systems.
A structure with few complexities fits into Toyota's plan
to amortize its large investment as rapidly as possible. "Toyota
continues to remain profitable, which is something that my
counterparts say is somewhat unique in the automotive industry,"
Street said.
"We are particularly schedule conscious. The entire
corporate profit structure is set on making vehicles on a
certain date. So no matter how many curve balls we throw at
the contractors, they have to be able to adjust and align
and roll with it and move forward with construction."
When completed, the plant will have the capability of manufacturing
150,000 full-size Toyota Tundra trucks per year. The site
can also accommodate expansion of manufacturing facilities
in the future.
Life in the Fast Lane W.T.
Byler of Houston began clearing 700 acres of the 2,700-acre
parcel in December 2003. In April 2004, Olmos Construction
Co. of San Antonio started excavating and grading 4.5 million
cu. yds. of dirt.
Lime was tilled into the dirt beneath the building to stabilize
the soil's expansive nature. "We put our money into subgrade
prep," Street said.
The plant building has a 7-in., unreinforced concrete slab
throughout most of it. In areas with heavy manufacturing equipment,
the slab was beefed up to about 12 to 14 ins. of reinforced
concrete with No. 6 or 7 double mats.
"We put our first piece of steel up in the air in November,"
Street said. "We put up 16,000 tons of steel in eight
weeks." At the peak period of erection, 8 cranes were
at work on the frame.
Work on everything past the steel frame started on Feb. 1,"
Street added. Power from San Antonio's City Public Service
was brought into the building on May 15.
In order to stay on schedule, a second shift was added. "A
lot of work is done on the weekends," Street said. "Double
time is paid on Sundays, so we try to steer clear of that."
With two contractor groups on the job, constant and ongoing
coordination is a requirement. To facilitate that, the conference
room walls in Toyota's main trailer are lined with sleek color
graphs, plans and other visual aids that are updated weekly.
"Toyota is very big on visual control. You can walk in
and figure out where you are," Street added.
Gary Jaslovsky, project executive for the Graycor/Byrne partnership,
called the job schedule intensive. "Getting our subcontractors
on board, getting all the submittals for the items they are
purchasing and getting them reviewed and approved was a significant
hurdle during the first three months," he added. "And
then the goal was getting the contractors out on the jobsite
and getting them oriented."
The demands of the tight schedule continued as work got under
way. "In the paint shop, there's work on basically four
levels in the building including the roof," Jaslovsky
said. "One of the challenges is keeping work moving in
the right order and the right sequence. There's a lot of involvement
with the field superintendents coordinating and directing
so the work can happen as it was planned to."
Keeping costs down has been more daunting. "We benchmark
our costs against previous projects and reduce them even more,"
Street said.
But Toyota has had to do so within what he called a new economic
model with rising metal, chemical and petroleum prices. "Structural
steel in the last couple of years has doubled along with everything
else in metal-siding, HVAC ductwork and things like that,"
Street added.
Supporting the Infrastructure
The plant site will include 1.5 to 2 million >> sq.
ft. of facilities for onsite tier one and two suppliers. Toyota
is also constructing a 93-acre railyard with 18 rail spurs
for the delivery of parts and supplies. Bids were recently
accepted for a 2-mi. test-track loop with a variety of special
surfaces.
TxDOT is supporting the project with improvements and expansions
of State Highway 422 and SH 16, which lead to the site. Bexar
County is improving and expanding roadways leading into the
plant.
Street described the design of the building situated on former
farmland as resembling "a large hay barn." The company
will extensively landscape 2,000 acres of the parcel and will
prepare 700 acres of greenbelt as parkland along the Medina
River and Leon Creek bordering the site as a gift to the city
of San Antonio.
"Toyota is always concerned about making sure they blend
in and become a part of the community," said project
architect Brian Spencer of Toledo, Ohio-based SSOE , the architect
and structural engineer for the plant. "They try to pay
attention to the aesthetics while maintaining a practical
approach."
|
Key Players
|
| Owner: |
Toyota Motor Manufacturing Texas Inc., San
Antonio |
| Project Architect/Structural
Engineer: |
Walbridge Aldinger Co., Detroit; Bartlett
Cocke General Contractors, San Antonio; Graycor Industrial
Constructors Inc., Homewood, Ill; Thos. S. Byrne Ltd.,
Fort Worth |
| Local Architect:
|
Marmom Mok LLP, San Antonio |
| Architect
of Record/Structural Engineer: |
Butler Rosenbury & Partners,
Inc., Springfield Mo. |
| Concrete
contractor: |
Concrete Structures LLC, Atlanta,
Ga. |
| Site Clearing
Contractor: |
W.T. Byler Co. LP, Houston |
| Excavation
Contractor: |
Olmos Construction Inc., San
Antonio |
| Concrete
Contractor: |
Detroit Building Group LLC,
Detroit |
| Steel Contractor:
|
Midwest Steel Inc., Detroit |
| Mechanical
Contractors: |
AJ Monier & Co. Inc., San
Antonio; LC Mosel Co., San Antonio; Stewart Mechanical
Inc., Louisville, Ky., Todd-Ford/Murphy Mechanical Contractors,
San Antonio |
| Electrical
Contractors: |
Martin Wright Electric Co.,
San Antonio, and Nitro Electric Co. LLC, Scott Depot,
W.Va., Alterman/Sachs, Fenton, Mo. |
| Plumbing
Contractor: |
Mueller & Wilson Inc.,
San Antonio, Todd-Ford Murphy Mechanical Contractors,
San Antonio
|
|