|
Schlitterbahn Slides Into Galveston
Despite design changes, weather challenges
and a devastating fire, Schlitterbahn will slide into Galveston
in December opening its third water park in the state. The
newest member of the Schlitterbahn trio is the first park
with closeable sections that make it an indoor-outdoor, year-round
entertainment destination.
By Jennifer Hiller

An aerial view of the 26.4-acre
waterpark site, owned by the city of Galveston.
(Photo courtesy Gilbane Building
Co.) |
Change has been the name of the game at the new Schlitterbahn
in Galveston, where Houston-based Gilbane Building Co. is
overseeing construction of the state's first indoor-outdoor
water park.
The $35 million park is located on 20 acres leased from the
city and six acres leased from Farmer's Marine Copper Works.
It is the third Schlitterbahn water park in the state. The
first was opened in New Braunfels in 1979 and the second opened
in 2001 on South Padre Island.
The 12-acre park has gone through numerous design changes
during construction.
"We don't have a 100 percent finished plan," said
Bob Walcott, project manager with Gilbane Building Co. "We've
been designing and building as we go. It's not a design-build
project, but some of it has turned out to be design-build."
The park site is near Moody Gardens, the Lone Star Flight
Museum and the city's airport. The indoor portions of Schlitterbahn
will open by December, and the entire park will open by mid-2006.
Ongoing design changes, along with a fire at the site, have
kept architects, engineers and construction crews hopping
since last summer.
A historic airplane hanger at the site burned to the ground
in 2004 while the project was in the design phase. The 1940s-era
hanger had been the focal point of the park's architecture
and was expected to house the main beaches, restaurants, utilities
and pumping equipment.
"We had to basically scrap everything we were working
on before because the hanger building was essential,"
said Julian Pittman, project architect with Houston-based
Jackson & Ryan Architects.
Architects redesigned the park to feature tent-like structures
and a "castle" structure at the center that houses
public areas and the bulk of the park's mechanical and pumping
equipment.
Site work started in November 2004. The Houston office of
Walter P. Moore, which handled civil and structural engineering
at the park, first had to relocate a large storm ditch that
ran through the center of the property.
Mac Ruffeno, civil project manager with Walter P. Moore,
called the storm ditch the main complexity of the project
sitework. "We had to maintain capacity," he said.
"That ditch drained a major portion of the airport property.
We had to route it around the project. That was the most important
thing for the surrounding population. There were quite a few
existing utilities that were owned by the city that we needed
to remove or relocate."
Then the low-lying site had to be raised for storm-flooding
protection. An initial elevation of 4 ft. was raised with
fill dirt to between 9 and 10 ft. throughout most of the park,
while the buildings sit above 12 ft., Ruffeno said.

A 480-ft.-long, open-flume water
slide is positioned on temporary supports 50 ft. above
a concrete river channel at Schlitterbahn Galveston Island
Waterpark.
Photo courtesy Schlitterbahn
Resorts. |
The water park is designed to withstand wind speeds of 130
miles per hour, while the tent theming above the castle building
is designed as a temporary structure.
"There are three rivers that each feed into each other,"
Pittman said. "The castle structure serves as a large
equipment room housing all of the behind-the-scenes equipment.
Above ground it's a public space with concession stands, lockers
and seating spaces."
The park's three-river system is modeled after the original
Schlitterbahn in New Braunfels. An estimated 4,000 ft. of
cast-in-place concrete rivers have a typical width of 20 ft.
"The whole park is interconnected," said Bob Walcott,
Gilbane project manager. "You can go from river to river
without getting out of your tube the entire time. The rivers
have been a challenge with all of the curves."
By August, 156,000 sq. ft. of tiling work had started on
the rivers. "We're pushing real hard to get the water
done so we can start testing it," Walcott said.
Erik Earnshaw, project manager for Beeler Guest Owens Architects
of Dallas, said his firm looked at some historical buildings
that were built around the San Marcos and New Braunfels area
at the turn of the 19th Century and tried to "extrapolate
from that into the project."
"We have some parapet walls on top of it and varying
balcony designs," Earnshaw said. "We wanted it to
fit into the nearby town square and the buildings around the
area."
Firm senior partner Jerry Beeler designed the building and
senior partner John Guest developed the master plan.
Brick on the first level links the new buildings to the church.
Stucco and Hardi-Plank siding face the upper levels, and the
roofs are composite shingle. The overall layout of the structures
is notched to prevent presenting a monolithic façade
that would dwarf the church. About 80 percent of the project
cost is in concrete, underground utilities and rides, he said.
The main castle building, which Walter P. Moore is overseeing,
is a cast-in-place concrete structure with basement sump area
to house the pumps and mechanical equipment that create the
flow of water around the park. All three river channels go
through the castle, which includes a structure to feed the
surfing wave generator and wave pool. A combination of mat
foundation and continuous wall footing was used to support
the structure.
Karim Zulgiqar, structural project manager with Walter P.
Moore, said the walls had to be designed to resist water pressure.
"We don't design a typical building for water pressure,"
he said. "Crack control was an issue. We design in a
way that we minimize concrete cracking so that even the chlorinated
water won't affect it."
Schlitterbahn's indoor section will include tube and speed
slides, a hot tub, a children's activity pool and the Tidal
Wave River and Beach. In the winter, water and air will be
heated in the mornings with blast furnaces.
A 30-ft.-wide covered area over the Tidal Wave River runs
1,200 ft., while the beach cover is 130 ft. by 160 ft. Both
structures will use a combination of aluminum frame and poly-carbonate
panels, which cost $2.5 million. The translucent panels will
allow natural lighting in the covered areas.
"The fabric roof lets some light though like at Reliant
Stadium," said Stephen Hegyesi, project manager with
Walter P. Moore.
In addition to the water rides, Gilbane is constructing nine
buildings onsite, including the $1 million, 24,000-sq.-ft.
castle building. Two large entry buildings, one 4,300-sq.-ft.
and the other 4,400-sq.-ft., will hold concessions, a photo
shop, cash-control rooms, retail space and ticket booths,
dressing rooms, lockers and restrooms. There will also be
two food and beverage buildings, two restroom buildings and
two electrical buildings.
And because crews work outside 100 percent of the time, weather
is always an issue. "November through January was tough,"
Walcott said.
|
Key Players
|
| Owner:
|
Schlitterbahn Resorts,
New Braunfels |
| General Contractor:
|
Gilbane Building Co.,
Houston |
| Architect: |
Jackson & Ryan Architects,
Houston
|
| Civil and Structural
Engineering: |
Walter P. Moore, Houston
|
| Rivers and Pumps: |
Sterling Engineering & Design Group, Austin |
| MEP Contractor:
|
EDSA Clower,
Salt Lake City, Utah
|
| Slide Contractor: |
The Core Group, Dallas;
NBGS International, New Braunfels |
| Concrete Contractors:
|
Keystone Concrete, Houston,
and Baker Concrete, Houston |
|