|
UT Power Project Generates Savings,
Ensures Reliability
By Scott Clark and Juan Ontiveros
The authors explain how improving power
plant operations at the University of Texas helped the campus
become more energy efficient.
|
 |
| Left:
Scott Clark, P.E., principal, Energy & Power Solutions
Group, Carter & Burgess Inc., Fort Worth; and
Right: Juan Ontiveros, P.E., director, Utilities and
Energy Management, University of Texas at Austin. |
The power plant at The University
of Texas at Austin is a model in self-sufficiency. The campus
cogeneration facility supplies 13 million sq. ft. in 140 buildings
with electricity, steam, compressed air, distilled water and
chilled water. Every type of refined energy on campus is self-generated.
In light of a rapidly growing campus, the university wanted
to ensure it had adequate, reliable and efficient energy systems
for many years to come. Three years ago, it embarked on a
comprehensive program to improve its power plant operations.
Its goals included identifying opportunities for efficiency
improvements and ensuring power reliability. With peak demand
at about 60 megawatts, the plant's total electrical generating
capacity of 85 megawatts was ample. However, its steam turbine
generator capacity consisted of only one 25 megawatt steam
turbine, installed in the 1980s, and two small, aged turbines.
The campus also needed an economical backup steam turbine
system to accommodate shutdowns and outages.
The university hired Carter & Burgess Inc. to conduct
a feasibility study and subsequently, the design of a new
steam turbine generator at the Hal C. Weaver Power Plant Complex.
The firm selected a Siemens 25 MW single-extraction, full-condensing
steam turbine generator.
Massive Equipment, Confined Space
During the project's programming stage, consultants looked
at numerous locations for the turbine/generator, which would
be 32-ft. wide by 70-ft. long by 30-ft. high. The power plant
complex consists of three separate buildings and adjacent
areas.
With the assistance of 3-D modeling, the decision was made
to locate the turbine/generator in a new addition to the existing
Power Plant Expansion Building. The site's location on the
front of the building provided access for equipment deliveries
- an important advantage as the largest piece weighed 141
tons. Another site clincher was that installation could be
executed within a non-operating power plant facility.
Coordinating the delivery and installation of 365 tons of
equipment within a confined space on the core of the campus
necessitated well-supervised traffic control and safety measures.
The site was also constrained by infrastructure systems.
A major duct bank for electrical conduits ran underneath the
turbine pedestal. To design and construct the pedestal structure,
the limits of the duct bank had to be physically located.
Special structural detailing was performed to account for
unequal spacing between the pedestal piers.
To minimize interference with piping and structural elements,
Bentley AutoPlant 3-D design software was used. Later, the
3-D model was utilized to create all of the 2-D construction
documents.
Steaming Ahead to Savings In
winter 2004, the turbine was in place and functioning. Based
on 2004 gas prices, it was projected to save $1.5 million
annually as a result of running 9.8 percent more efficiently
than the existing turbine. In addition, the turbine will provide
savings related to efficiencies gained during scheduled and
unscheduled outages. At a total cost of $15.6 million, the
project had a seven-year payback when gas prices were $4 per
MMBtu. Given escalated gas prices, the payback period on the
project has gone down considerably from the original feasibility
study estimate.
The existing 25 megawatt turbine, in good condition, is kept
on standby. Previously, when the old turbine experienced unscheduled
maintenance and planned outages, the campus relied on the
two small steam turbines built in the 1940s and 1950s that
could incur hefty gas-usage penalties. The two older turbines
were used as spinning reserve for steam in the event the 25
megawatt steam turbine tripped off line. This resulted in
continuous use of low-efficiency steam generation. When the
new steam turbine bypass system came on line in October, the
two small turbines were completely shut down. This project
will result in an additional savings of $750,000 in annual
gas costs.
Complementing the new turbine was the replacement of a 1950s
cooling tower with a new Marley (formerly Ceramic Cooling
Tower) tower capable of running all generation equipment.
Carter & Burgess supplied the engineering and architectural
design services for the $8.4 million cooling enhancement project.
The new tower and turbine increased the campus's electrical
capacity from 85 megawatts to 110 megawatts, giving the university
the option of selling power to the grid. Given the campus's
peak load of about 60 megawatts, the university could sell
up to 50 megawatts. Currently, it is evaluating the possibility
of selling excess power to a wholesale electric company; under
certain conditions, it may be able to provide power to the
grid at an economically attractive rate.
|