|
Know Your Rights: Prompt Payment
Act and Termination Remedies
By William Coats.
We frequently receive calls from contractors and subcontractors
who, for a variety of reasons, are not being paid by an owner/general
contractor and for whom bond and lien remedies are not available.
They want to know how they can get paid. In some instances,
the contractor or subcontractor has been terminated or has
walked off of the job and wants to know what materials, equipment
and supplies can be removed from the site. Consider the following
when dealing with these issues.
The Prompt Payment Act
The Texas Property Code Section 28.001 ("Private Work
Prompt Payment Act") deals with payment to contractors
and subcontractors for "properly performed work and suitably
stored materials" on private work projects. The terms
of the act require the owner to tender payment to the general
contractor 35 days from the date of the submission of an invoice
"[f]or an amount that is allowed under the contract for
properly performed work." The general contractor, in
turn, must pay the subcontractors for the portion of the owner's
payment that is attributable to work properly performed no
later than 7 days after the contractor receives payment by
the owner. If the parties are embroiled in a "good faith"
dispute regarding a portion of the work, the party withholding
payment can withhold no more than 100 percent of the difference
between the amount it believes is due and the amount the invoicing
party claims is due. Interest accrues at the rate of 1.5 percent
per month or 18 percent annually on overdue payments. The
terms of the act cannot be waived or altered by contract and
attempts to do so are void.
Work suspension is also an available option under the terms
of the Private Work Prompt Payment Act. However, we suggest
that work stoppage or suspension only be employed as a last
resort. This is a risky strategy; if the reason for nonpayment
is failure to perform in compliance with the contract, the
contractor or subcontractor may expose themselves to claims
for corrective work, completion costs, damages for delay and
a host of other damages and penalties.
The Public Works Prompt Pay Act, which is found in Texas
Government Code section 2251.001, has very similar terms to
the private work act. On public projects the owner must tender
payment 31 days after receiving the invoice and the contractor
must pay the subcontractor no later than 10 days after the
contractor receives payment. Interest accrues at 1 percent
per month. As with the private work act, payments for the
disputed work can be withheld.
One of the aims of these statutes is to penalize heavy-handed
owners and contractors who hold ransom undisputed amounts
as a means of gaining an advantage in the dispute over the
remaining amounts. This is accomplished through interest penalties.
Removing Equipment and Materials Post-Termination
When a contractor or subcontractor quits or is fired, one
of the issues is who owns the materials and equipment that
the contractor or subcontractor delivered to the jobsite.
- Transfer of Title-- Although this is a generalization,
title typically passes upon delivery. Review the contract
documents for provisions that discuss transfer of title
or even assignment by the contractor or subcontractor of
the equipment, materials and tools. If title has transferred
and/or an assignment provision exists, the materials and
equipment stay at the jobsite.
- Conversion-- Both parties need to be aware of the contract
terms and transfer of title of the materials and equipment
or they may face a claim of conversion. If equipment or
materials are being wrongfully withheld, a demand needs
to be made for the return of the items that is fairly specific
and accurately describes the items sought. A temporary restraining
order or injunction are methods to consider using to recover
the items if the value of the items justifies the cost to
do so.
- Trespass-- If the termination has been particularly acrimonious
and the contractor or subcontractor has been ordered to
stay off of the jobsite, the parties will need to make arrangements
to permit the return of equipment or materials (if any)
which the subcontractor and/or contractor is entitled to
remove. Returning to the property to recover equipment without
permission may subject the terminated contractor to a charge
of trespass. One court held that a contractor's abandonment
of a large pipe that did not conform to the project specifications
and was not useable constituted a trespass and the contractor
was liable for the costs to remove the pipe.
|