|
Liquidated Damage Provisions: Are
They Always Enforceable?
By William Coats, director, member
of the executive committee and the head of the construction/surety
section of Houston-based Coats/Rose.
This month, we provide a brief
overview of the analysis that the Texas courts apply when
evaluating liquidated damage provisions and discuss steps
that may be utilized to minimize the effectiveness of potential
challenges in subsequent litigation.
Construction contracts often contain
a liquidated damage provision that provides for payment a
stipulated amount in the event that work is not completed
within a specified period. Owners often impose these provisions
to ensure the timely performance of the work by penalizing
the contractor if the work is not completed on time. However,
this type of rationale may result in the liquidated damage
provision being held to be unenforceable if it is challenged.
The universal rule for measuring damages for a breach of
contract claim is just compensation for the loss or damage
actually sustained. As a result, a party should generally
not be awarded more or less than their actual damages. Although
competent parties generally have the right to make their own
bargains, this right is not unlimited.
The same is true for liquidated damage provisions. Courts
will enforce these provisions provided that they are not inconsistent
with the general rule of just compensation. As a result, a
liquidated damages provision will generally be upheld if it
was created by the parties in an attempt to estimate, in advance,
the damages that will be suffered in the event of a material
breach.
If the provision was created to ensure timely performance
by penalizing the other party if work is not completed on
time, the provision will be held to be a penalty. In such
a case, the provision is unenforceable and the non-breaching
party will still be entitled to recover its actual damages.
In evaluating whether a provision is an enforceable liquidated
damage provision, Texas courts have looked to the following
factors:
- Whether the amount stipulated in the contract is a reasonable
forecast of just compensation for the harm that is caused
by the breach
- Whether the harm that is caused by the breach is one that
is incapable or very difficult of accurately estimating
- Whether the amount of liquidated damages to be assessed
is disproportionate to the amount of actual damages incurred
- Whether the liquidated damage provision applies equally
to both material and minor breaches
- Whether the liquidated damage provision was not intended
to provide fair compensation for the breach but to secure
performance of the contract.
Owners have often attempted to address these factors by drafting
the liquidated damage provision to specifically state that
the provision is not intended to be a penalty. To the extent
that the provision has been negotiated, this language may
be of some assistance to the owner in attempting to prove
the parties' intent. It should be emphasized, however, that
such language is not binding on the court.
Courts analyze the liquidated damage provision to determine
whether it was an actual attempt by the parties to estimate,
in advance, the damages suffered as a result of a particular
breach. As a result, the liquidated damage provision should
be tailored to the particular contract. When the owner uses
the same amount for liquidated damages in all of its contracts,
courts will often find that the provision was intended as
a penalty and, therefore, unenforceable. Similarly, if the
same amount of liquidated damages will be triggered by either
a material or minor breach, courts have held that the liquidated
damage provision is unenforceable even if there has been a
material breach.
A party who is seeking to craft a liquidated damage provision
that would be upheld by the Texas courts should consider a
pre-contract analysis as to what the potential damages could
be if the work were not completed on time. The analysis should
be documented in the file. Moreover, if the parties are able
to discuss this analysis and negotiate the stipulated sum
to be paid, it will lend more credence to the reasonableness
of the estimate.
Provisions should be crafted so that they do not apply equally
to both a minor and material breach. A liquidated damage provision
that applies equally to "the failure to perform any obligation
required by the contract" should be avoided.
As well, the use of the same stipulated sum for every contract
should be avoided as it undermines the contention that the
stipulated sum was intended as a reasonable estimate of the
damages to be suffered for that particular contract.
|