|
Legislature Steps up to the Plate
on Sovereign Immunity
In mid-June, Governor Rick
Perry signed HB 2039 into law, allowing contractors to sue
local governmental entities directly for breach of contract.
By Joseph P. Dirik
Joe Dirik is a graduate civil engineer
and attorney. He is a member of the construction law practice
group at the Dallas office of Jenkens & Gilchrist, PC.
At the 11th hour, the Texas Legislature passed HB 2039, an
important bill waiving the state's immunity against suit for
certain lawsuits brought against local governmental entities.
Gov. Rick Perry signed the legislation in mid-June.
The legislation permits contractors to bring suit directly against
municipalities, public school districts, junior colleges and
special purpose districts or authorities. The suit may be brought
in state court or in an arbitration proceeding if the parties'
contract so provides. It does not apply to counties or units
of state government such as TxDOT. Moreover, HB 2039 does not
waive sovereign immunity to suit in federal court.
Texas was among a minority of states that allowed the doctrine
of sovereign immunity to prevent a contractor from seeking
redress in court against the state for breach of contract.
The concept that the state was immune from suit in its own
courts was itself a judicial creation.
The doctrine of sovereign immunity derives from the ancient
concept that "the king can do no wrong" and pre-dates
the Texas Constitution. In 1970 the Texas Legislature enacted
the Texas Tort Claims Act, waiving the state's sovereign immunity
for torts in certain circumstances. HB 2039 does not waive sovereign
immunity to suits for negligent or intentional torts.
Contractors are now able to sue local governmental entities
directly for breach of contract. The legislation limits damages
awarded to:
- the balance due and owed under the contract as amended;
- the increased cost to perform the work as a direct result
of owner-caused delays or acceleration;
- the amount of change orders or additional work the contractor
is directed to perform; and interest as allowed by law.
The bill expressly disallows awards for the following damages:
- consequential damages (for example, no lost profits);
- exemplary (punitive) damages; and
- unabsorbed home office overhead (such as Eichleay formula
charges).
Furthermore, attorney's fees cannot be awarded to any party
in the suit or arbitration unless the contract with the local
governmental entity expressly authorizes the prevailing party
to recover its attorney's fees.
HB 2039 applies to contracts executed after September 1,
2005, the effective date of the bill.
Because the bill does not limit the manner in which the owner
might order extra work or cause delays or acceleration, I
believe contractors can pursue claims for constructive changes
as well as for changes directed in writing.
Note that the parties must comply with any prerequisite to
bringing suit identified in their contract. For example, the
contract may require that as a prerequisite before bringing
suit the parties undergo non-binding arbitration or mediation.
The local government entity is free to raise any defense
against a claim other than a bar against suit based on sovereign
immunity.
So what happens to contractor claims against state agencies?
While I believe there is a strong chance that the 80th Legislature
will completely waive sovereign immunity in certain contract
claims, the procedures outlined in Chapter 2260 of the Government
Code still apply to most claims. (For example, some contracts
subject to Transportation Code Section 201.112 are not covered
by Chapter 2260). A contractor claiming breach of contract
must provide written notice of the claim within 180 days after
the date of the event giving rise to the claim. The agency
examines the claim and any possible counterclaim, and attempts
to negotiate (or mediate, if agreed) with the contractor.
The contractor may request a contested case hearing if the
claim is not entirely resolved within 270 days after the date
the claim is filed. The agency then refers the claim to the
State Office of Administrative Hearings for a contested case
hearing.
The state is required to pay valid claims for $250,000 or
less, but only if money has been or is later appropriated
by the Legislature. For claims of $250,000 or more, the Administrative
Law Judge recommends to the next legislative session that
the Legislature either appropriate money to pay the claim
or not appropriate money to pay the claim and deny consent
to suit. In other words, for any claim above $250,000, an
ALJ's determination of a valid claim is not binding on the
state.
But the SOAH process is not necessarily the end of the story.
The Texas Supreme Court hinted, and several courts of appeals
have found, that the state entity may waive its sovereign
immunity in certain situations. The state, for example, waives
immunity from suit when it brings an action against a contractor
in state court. In such a case, the contractor is free to
bring a counterclaim directly against the state.
Several cases involving waiver of sovereign immunity are
pending before the Texas Supreme Court. I believe it is possible
that the Court may permit contractor suits under certain situations.
The 80th Legislature, however, should step up to the plate
again and address waiver for state agencies in the next session.
HB 2039, and the expected changes to come, will drastically
change the way contractors work with Texas public entities.
|