The final costs of the DFW Terminal Development Program are still in review, but initial estimates place the cost somewhere between $1.5 billion and $2 billion, with funding to come from bond sales, available capital and other sources.
The renovation project includes facelifts for passenger areas including ticketing, security and concessions. Plans also call for the replacement of terminal systems such as electrical, plumbing, heating and cooling, security, conveyance and telecommunications.
Current plans call for construction to begin in early 2011. Terminal A will be the first terminal completed, in 2014, and the entire project should be complete by the end of 2017. The construction phase requires one-third of each terminal to be shut down at a time.
Design concepts call for the consolidation of concessions areas into villages reminiscent of DFW’s International Terminal D, which opened in 2005 at a cost of $1.2 billion.

Sign in to Comment
To write a comment about this story, please sign in. If this is your first time commenting on this site, you will be required to fill out a brief registration form. Your public username will be the beginning of the email address that you enter into the form (everything before the @ symbol). Other than that, none of the information that you enter will be publically displayed.